El Paseo construction reaches milestone, as crews work to complete project this fall

PALM DESERT, Calif. (KESQ)-- Construction along El Paseo continues, as the project reaches a new milestone. This week, both sides of the road are back open from the 74 to Portola.

The City of Palm Desert has most recently completed the third phase of the El Paseo Street Rehabilitation Project. This phase included improvements to the westbound lanes, north side of El Paseo between San Pablo Avenue and Portola Avenue.

Immediately following completion of the north side, crews shifted the traffic control to the eastbound lanes, south side of El Paseo, between San Pablo Avenue and Portola Avenue. Crews are now working on pavement removal and asphalt installation for this segment, with work scheduled to take place through August.

The final phase will begin in September. Intersections at Portola and San Pablo will be done at night in September, and mid-block crossings will be added after all of the paving is complete.

For updates on the project click here.

News Channel 3's Tori King is speaking with the city about this final phase, see her coverage at 4, 5, and 6.

Article Topic Follows: News

Jump to comments ↓

Author Profile Photo

Tori King

Tori King joined KESQ News Channel 3 as a reporter and anchor in October 2023. Learn more about Tori here.

BE PART OF THE CONVERSATION

News Channel 3 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.